C2C core volunteers organize frequent work trips for the purposes of grading tread, brushing, removing downed trees and invasive weeds, placing signage, and other maintenance. We need volunteers (individuals or groups)! Check back here for dates and times, or contact us to request info about upcoming opportunities. All trips meet in the morning at the northwest corner of the BiMart parking lot at 53rd Street and Philomath Blvd, to carpool to the work site.
Wear sturdy boots, a long-sleeved shirt, and pants, for protection from tools as well as vegetation such as stinging nettles, which are found overhanging the trail in some locations. Work gloves are a good idea for hiking through some of the brushy areas. Bring a lunch, water, and a hard hat if you have one. We will supply a hard hat if you do not have your own. We will supply all the tools necessary. You need to download, sign, and date this liability waiver form before you will be allowed to participate in a work party. A separate form for those under 18 years of age is available here. Once you have done so, bring the signed form to the outing meeting departure location, or mail it in advance to the C2C Trail Partnership, P.O. Box 1562, Corvallis, OR 97339-1562, or email us a scan of the signed form to contact@c2ctrail.org. When we receive the form or the e-mail, you will be added to our “explorers” e-mail notification list, and you will then be alerted to the next work party.
Work Party Summaries by John McNair
10/18/2026: We had a small but productive group brushing most of upper Gopher Ridge. Randy had previously used the billygoat to make a path on part of it, so we brushed to his turnaround spot. Some of us lopped and raked while others brushed using two of the new machines. Talked briefly with two cyclists who had camped at Big Elk and were on their way to the coast. Another beautiful day in the woods.
10/16/2026: We had an excellent work party yesterday brushing Lower Gopher Ridge and Gopher Creek. Randy and Mary rented a walk-behind “billygoat” brusher, which worked very well, especially considering the steepness. Fred and Jan used the weed hackers to hit the sides not covered by the walk-behind. This area has always needed major maintenance. It was great to get both sections done for a while. Weather was perfect. Another great day in the woods. 
10/4/2026: We had a productive work party. Five were brushing and two were cleaning tread. We worked on Grant creek, part of Hogback and lower Bull Run sections. Regrowth was not as bad as anticipated, but there are other sections a lot worse which we will tackle in the future. We also cleaned up the “Y” intersection of Grant Creek Road and Hilltop Road. Lots of lobster mushrooms on Bull Run. Thanks to Randy and David for the tread work and Fred, Jan, Joe and Steve for the work brushing. Good progress. Should last till May or June. I did bump into two bikers on their way to the coast after they spent the night at Big Elk Campground. They said the water at the campground was not great, but OK. 
10/2/2026: We had another successful work party wrapping up the Northstar reroute. Signs are in and all we need are hikers. We added four more signs and removed a few. We added a few runout drains. We rehabbed the old trail so it will not be used and nature can take over. Randy and Mike removed the last stump in the way, so the trail looks great. Mary and Fred cleaned old tread so the trail leading to the reroute is clear. Jim started to log all the data for the new signs. The tread on the reroute looked very good after the rain. Randy and Mike also put in two large water bars on the Manulife road past the reroute on the way to the tunnel. The existing puddle was too much to drain using hand tools, but the water bars should help a lot. There was no indication of logging traffic through the CG gate. We did see a logging show about two miles north of us. They probably were using another gate farther north. Weather was glorious. Another great day on the coast.
9/19/2026: We had a very productive work party on the Northstar reroute. I think we are 95% done now. We installed two Carsonite signs: one on Beaver Creek road and one about a half mile in at a wide spot which needed a sign. We then went to the work site, where we met Joe and his dogs. We worked on the tread and Randy chopped a lot of roots. To finish, we need to remove the two original signs and the temporary ones. We need to add two signs at the top and bottom and rehab the original trail. Also a would-be-nice job is to drain the large puddle on the road toward the tunnel. The soil is so soft, there will need to be more finish work on the tread next spring, after the winter rains. Another fine day on the coast.

9/16/2026: We had another successful work party progressing on building a reroute trail around the Northstar property, near Ona Beach. We had fourteen workers and got a lot done. We borrowed a loaner key from Starker for their west gate and were eventually able to drive to the tunnel, reducing our walk with tools considerably. The parking area needed work, so we cut weeds and made a major improvement for future visits. Some went to the Northstar reroute work site and started cutting downed trees blocking a preferred path. We cleared most of the path and made good progress determining where the tread should be. We transplanted about 10 small cedars Manulife had planted last year. I added a few small signs to ensure any hikers did not stray off the newly constructed trail. When we were leaving, we happened on two backpackers heading for the beach. Evidently, the signage for the reroute is working. Another outstanding day near the coast.



9/4/2026: Had a tougher than usual work party. We had eight helpers, of which three were from the coast. I intended to access the work site through the Beaver Creek gate and drive up Simpson Creek Road to Manulife property. Unfortunately the C2C lock was removed from the gate, so we had to access it via the Starker gates (up Wolkau Road and Wright Creek Road). This turned a one-mile hike into a five-mile hike. The weather ended up being great, but we got dumped on driving home. Our work site was a new sustainable trail through the Manulife clearcut, which is necessary to get around a Northstar property access ban. We brushed several possible paths through the clearcut brush and eventually determined what seemed the best path. We also brushed the bottom path around the draw on the lower road, which is part of the original C2C. The old existing trail climbing the hill is washing out and badly needs brushing. Since the section is being replaced, I opted to leave as-is. It will be rehabbed once the new reroute is finished, and covered with debris to prohibit hiking traffic. We now have a brushed corridor for fine-tuning the trail tread and the turns. We have a lot of saw work to cut many downed trees and even more stick-chucking to do, but we did make a lot of progress. Was a relief about fire danger, as the vegetation was very wet. The trees Manulife replanted are cedars, differing from the regular Douglas fir. Evidently Starker will soon be logging north of the Simpson Creek area and using Simpson Creek Road and the Beaver Creek gate as the haul route. Do not park between the gate and Beaver Creek Road. There is room for six cars to park across the road from the gate. Another great day in the clearcut.

8/22/2026: We accomplished the major part of the work to open the reroute. Thanks to all who helped. We had a really big, excellent group. We split into three groups to check on the water source and add stickers to blank signs, brush a path through the blackberries on the CRC road, and install new signs on the east end. The parking area on the Forest Service road was improved for more cars. We had sixteen people and seven cars, but it worked out. We also had three new people who were from the Portland area and volunteering so they could ride the MVBC trip this fall on the C2C. We had five people who live on the coast: Seal Rock, Toledo, Newport and Siletz! Weather was fine, and we even got some mist at times. The remaining work is:
- Complete kiosk at Starker gates and update 5081 kiosk.
- Remove closure signs on 5081 gate put there in November.
- Do a test walk on section east of Starker gates to 5081 gate to check clarity of installed signs.
Another great day in the woods.
7/22/2026: Another successful trip to improve the reroute near the coast on Starker land. We added three signs along the side road down to the water. We then cut a trail in and around the berm next to the water source. The water was still running. Dawn and Terry cut the tall grass east of “the tunnel” connecting Starker and Golden Pond land. Steve cut a tree on the road and brushed the path to the water. There was thunder around us for about 1.5 hours, but we stayed dry.





6/28/2026: We had four workers today brushing in the 5081 area. We brushed the Wright Creek water trail and dug a small sump for better water access. Probably should embed a bucket eventually. We went to the east end of the new reroute section and brushed a parking area and both sides of Rd. 248. Another great day in the woods.
6/26/2026: We had five workers today. We had four brushers going and almost cleared the whole Palmer Mountain section. The highlight was that we met about eight backpackers going west on their second day. They started at Big Elk. The 5083 road was very overgrown, even though it was brushed last winter. The mucky dips on the east part of 5083 were cleaned up and fine. The parking area Randy installed last year is working well. Could use an anti-weed treatment though. The trail adopters tried a mountain beaver suppression technique to stabilize the tread around colonies, and it seemed to work well. There are a lot of signs of them. Fergus Creek was running, but only at about a gallon a minute. The creek crossing has moved upstream about four feet, due to erosion. We looked at the tread and the future possibility of improving the trail to bike standards. We did get rained on walking up. Another fine day in the woods.

6/24/2026: We had a big crowd of workers today, which allowed us to quit a bit early. We brushed Hogback and Grant Creek and repaired the leaning sign on Van Eck. Also did some tread work, removed a troublesome tree, and cleared some road signs of weeds for better visibility. Horseflies were out, but few casualties. Another great day in the woods.
6/17/2026: Successful first use of a “BillyGoat” walk-behind brusher, today, on Branch Creek and the top half mile of Gopher Ridge. We made two passes on each, leaving a mowed walking space of about four feet. The mowing itself took only two hours, but the renting, loading, reloading and driving made it a six-hour day. This method goes quickly enough that it may be possible to mow all of the C2C road-to-trail sections in one long day. Helpers with handheld brushers could then knock the encroaching vegetation back to the edges of the roadbed instead of spending hours grinding the tread.

5/31/2026: We had eight workers to brush Sugarbowl and Van Eck. We got it done with four brushers. While we were working about 10 bikers went past. One thanked us and commented that the section was notorious as “nettle alley.” We were able to get the path cleared before they arrived. Mary gave some advice and training on water bars and drainage. Also cut a small tree hanging over the trail. Found some shiny geranium on Sugarbowl. Will notify USFS. Also some poison oak on sidehill single track. Another fine day in the woods.
5/29/2026: We brushed on lower Gopher Ridge and Gopher Creek today. We had five brushers going and eight total folks working. Lower Gopher Ridge looked amazing after the crew finished. Sunday, we will be working on Sugarbowl and Van Eck. The nettles will probably be quite tall there. We wanted to get as much of the trail brushed as possible for the big run tomorrow. Another fine day in the woods.


5/27/2026: We had our first brushing work party of the season. We brushed most of upper Gopher Ridge and Bull Runs. We had five brushers going, but still didn’t finish either section. The nettles are about four to five feet high, so definitely time to start. The new brusher I bought Tuesday worked like a champ. Steve and Jan brought their own brushers. Lots more left. Another fine day in the woods.
5/15/2026: We had a crew of five. We installed four blank signs on the reroute. It was a long way to carry both heavy sign installer tools. We widened the ramp up to the old gate and brushed both paths around the two berms. The road is going to take more brushing maintenance. We barely dodged the rain, but it was still another great day in the woods.

5/13/2026: We had another good work party adding signs and cleaning tread on the west side of the reroute. We saw two different Starker trucks patrolling the area, so be sure to get your Starker permit.
4/27/2026: Tread work on Palmer Mountain Trail:
4/9/2026: We worked in the Wolkau Road area. We moved the red cow gate, old fenceposts, and the remains of the kiosk, to the Starker double gates at the end of Wolkau. The scouts had set the kiosk into concrete, so extracting it whole was not possible. Randy cut the posts so all C2C material is now off Wilson property. We then walked to a water source downhill from the east gate, and took photos for later improving the path. We then walked west to the tunnel between Starker land and GP/Manulife. There was some debris from the winter. The elk had found the path and used it regularly, so it was not smooth or easy to walk. Randy slaved away cleaning tread that connects the GP/Manulife road to the tunnel. On the way home we cut the tree that fell across the Gopher Creek section. Another fine day in the woods.
2/25/2026: Some of us went to iron out some root issues on Lower North Ridge Trail, on the east side of Marys Peak. Others went farther west on the trail to tackle some downed trees on FS roads 3127 and 5081.

2/2/2026: A small crew went out this morning to do some more work on the parking area between Old Peak Road and the Lower North Ridge Trail: drainage and some pothole filling. We hope to spread more gravel soon. Thanks to Jeff, Fred, John, Randy and Mary.

1/14/2026: We had eight workers today, mostly on Lower North Ridge Trail (LNRT). Ken and Steve went separately to Sugarbowl to cut downed trees there, and then to Old Peak Road to clear logs. Big thanks to adopter Theo, who scouted the trail yesterday and let us know the location of the trees. We cut two 20-inch trees over the trail and two smaller trees near the top. We added roofing paper on a small bridge to make it safer. We drained puddles and holes in the parking lot at the base of LNRT. We cleaned tread for a significant part of the upper trail. We staged timbers and posts near the trail to use for future cribbing and steps. We checked out old cribbing on one turn, which was in excellent shape. Corvallis was in deep fog all day, but we were in sunshine when we got to the woods. We had two NEW helpers today. Another great day in the woods.

1/9/2026: We had six workers and covered a lot of trail sections. We surveyed/cleared Bull Run, Branch Creek, Hogback and Grant Creek. We cut about 10 logs on the trail tread. Most were small, but a few were about 12″. We tossed a lot of smaller sticks and branches. There was wind damage out there, but nothing major. There were signs posted on Hilltop Rd. (USFS 31) indicating logging trucks on Bull Run Road (USFS 3119), but we didn’t see any nor much evidence of heavy traffic. We used several parking areas that we had recently improved. They are looking tired and need some raking and smoothing. Our old-timers will note that the toilet bowl at the top of Branch Creek is now gone. Randy and Sabrina worked on placement of large rocks at the creek crossing just west of the Grant Creek kiosk.
1/3/2026: We had 14 workers cleaning woody debris and logs off the newly brushed 5083 road. Thanks to all who came out, especially the strong contingent from the coast. We cleaned and improved 13 water bars, improving the driving experience. All of the work hours required by our grant have now been met! We found a lot of shiny geranium (invasive) on the roadside, so we will contact the Forest Service botanist, who won’t be happy. We dodged the rain, so a good time was had by all. Another great day in the woods.

11/28/2025: We had 11 hard workers turn out to build some new trail. We hope this will be part of the reroute, which was made necessary by our C2C Trail closure around mile 54-55.
10/8/2025: Four of us worked on Gopher Creek section. We brushed the whole thing and did some hinge work which sharpened up a portion. We then added cribbing to a turn on the way down from the landing. More needs to be done, but made good progress today.
9/24/2025: We had six in today’s work party. We brushed the Grant Creek section, cleaned hinge on most of the steep switchbacks, and added cribbing to a turn near the top and three more posts to the bottom of the steep section. The stream was dry and a new 10-inch log had fallen on the creek crossing. Weather was superb. Saw three to four log trucks rolling down Hilltop (FS-31). Checked the kiosk and there were still cards in the box. Saw a few lobster mushrooms and some chicken-of-the-woods.
8/26/2025: We had a good crew who blasted the middle section of Gopher Ridge with weed-eaters and rakes and loppers and a bush-hog. The middle part has often been missed when we tackle this stretch. Most of it got a good haircut. Randy, Mary and Robert stayed later to attend to widening cuts in the bumps, easing access.
8/10/2025: The weather was supposed to be very hot, but where we were it was tolerable to pleasant. We brushed and raked four potential parking pads on Bull Run Road (FS-3119). They are ready for rock, but could use some follow-up if possible. We also reinstalled the short culvert at the bottom of Lower Bull Run. Then Randy, Mary and Holly went off to work on upper Gopher Ridge bumps. The rest of us went to install more steps on Hogback. We put in six more.
7/6/2025: We had great day brushing Sugarbowl and Van Eck sections. We had six people working. We had all three big Honda brushers going the whole time and also a small Stihl, which worked OK, but was underpowered for the work. One party of three went to the bottom and to the Van Eck road and water trail, which they brushed. Ken intends to install a carsonite sign at the top of the water trail to make the water source more obvious. A second party blasted the top road of Sugarbowl and the nettles took a savage defeat. We had five bikers pass by. They did appreciate our brushing efforts. We did discover a new tree over the trail. A big alder, which Randy has in his sights. It was quite nice out there, discounting the horse and deer flies. I walked part way down the sidehill switchbacks to see how the trail was holding up. It is almost 10 years old and is in good shape. All the work Ron and Gary put into the turn cribbing was well worth it. Ken reported that the drainage on Van Eck we worked on this winter seems to have improved the tread. So, a job well done! Another great day in the woods.
6/28/2025: Yesterday we had a long fruitful day clearing the Palmer Mountain section of brush. We had eight workers. Besides brushing the trail, we thoroughly cleared the parking area and the turn-around nearer the berm for possible future parking pad improvement. The 5083 road was very overgrown with new growth. Rather discouraging, since we are having the roadsides thoroughly brushed each year. We installed a new carsonite sign for the newly USFS-approved path to a better water source of Fergus Creek. The original Fergus Creek crossing still has adequate water, but the level is falling fast. Also, Steve added stickers to the trail signs which match the day hikes from the new brochures. Three through-hikers went by while we were working. They were on their third day. Another great day in the woods.
5/25/2025: We had another successful work party brushing the rest of Hogback and all of Grant Creek. We had nine workers. We brushed, lopped, raked and did some tread work. I am particularly happy with how the switchbacks of Upper Grant Creek have held up. I still remember Rollie, Amber and Curt moving a lot of dirt off that steep hillside. It looks great. There were probably twenty or more bikers going up Hilltop (FS-31). There was one day-hiker going up from the Grant Creek parking area. Another great day in the woods!
4/12/2025: We had another very successful work party today, thanks to a lot of help. We had a new couple and one who was there the second time. Randy and David separately went to Gopher Ridge to clear the logs on it and then possibly do some needed brushing. The rest (eight of us) went to Van Eck and Sugarbowl. Steve and Theo cleared the remaining logs on the two sections, so the list of logs to remove is complete! The rest of us worked on drainage and putting in a very short trail so hikers can access water from Sugarbowl Creek. It was flowing beautifully. The trail had short sections that were very soggy, making this an excellent time to improve the drainage. Ken and Louisa organized us to make major improvements. More to do, but I was impressed by what we did in a few hours. This has been an ongoing problem. The final task was installing a carsonite sign at the road/trail junction on Van Eck. I still have not come up with a decent remote water symbol, but we installed the sign for future stickers which will direct hikers to nearby water.
